On October 2, 2004, the voters of Klein passed a bond referendum for $224 million dollars to address growth, safety and security, 21st century learning technology and equity. Below is a list of projects that are completed or are in progress. You may also visit the other links provided at the left of this page, to find out the history of the 2004 Bond Plan, the demographic study and prior bond elections in Klein. |
| Year Initiated |
Project
|
Cost
|
*Status |
|
2005
|
PE Facilities - Kuehnle, Mittelstadt, & Roth |
$2,618,000
|
C
|
|
2005
|
Miscellaneous Projects - Northampton, Brill, Haude, Greenwood Forest, Nitsch, & Schultz Clinics; Hildebrandt & Wunderlich Science Lab Remodels; Various Athletics & Paving Jobs |
$3,413,200
|
C
|
|
2005
|
Mold Remediation/Rebuild - Northampton, Greenwood Forest, Haude & Epps Island |
$8,000,000
|
C
|
|
2005
|
Rebrick - Klein High School Auditorium |
$448,888
|
C
|
|
2005
|
Benignus Elementary School |
$10,788,535
|
C
|
|
2005
|
Krimmel Intermediate Design |
$750,000
|
C
|
|
2005
|
Vistas High School of Choice Site Acquisition (5.91 acres + building) |
$1,325,000
|
C
|
|
2005
|
Vistas High School of Choice |
$2,721,959
|
C
|
|
2005
|
Addition/Remodel - Klein Forest High School |
$12,712,585
|
C
|
|
2005
|
Three Temporary Buildings |
$204,370
|
C
|
|
2005
|
Stadium Lighting - Klein Intermediate, Doerre & Strack |
$408,664
|
C
|
|
2005
|
HVAC Projects - Klein Oak, Klein Forest, Klein High, Strack, Brill, Nitsch |
$1,444,325
|
C
|
|
2005
|
Fire Alarm Projects - Benfer, Haude & Wunderlich |
$389,920
|
C
|
|
2005
|
Energy Conservation Projects - Ehrhardt & Nitsch |
$250,000
|
C
|
|
2005
|
Roofing Project - Brill, Klein Intermediate, Maintenance Center |
$555,730
|
C
|
|