On May 10, 2008, the voters of Klein passed a bond referendum for $646.9 million dollars to address growth, renovations, safety and security, and technology. Below is a list of projects that are completed or are in progress. Additional information is provided by clicking on the underlined projects. You may also visit the other links provided at the left of this page, to find out the history of the 2008 Bond Plan, the demographic study and prior bond elections in Klein. |
| Year Initiated |
Project |
Cost |
*Status |
|
2008
|
Mueller Elementary |
$15,003,029
|
C
|
|
2008
|
Ulrich Intermediate |
$25,456,920
|
C
|
|
2008
|
High School #5 |
$116,767,909
|
D
|
|
2008
|
Klein Oak/Klein Collins Additions |
$21,010,813
|
C
|
|
2008
|
South Transportation Center |
$4,306,000
|
C
|
|
2008
|
2009 Facility Renovations |
$9,050,000
|
C
|
|
2008
|
2009 Interior Renovations |
$2,434,518
|
C
|
|
2008
|
2009 Fire Alarms |
$1,004,992
|
C
|
|
2008
|
2009 Energy Conservation |
$778,815
|
C
|
|
2008
|
2009 Mechanical, Electrical, Plumbing |
$5,889,550
|
C
|
|
2008
|
2009 Job Order Contract - Misc. Renovations |
$301,447
|
C
|
|
2008
|
2009 Roofing |
$1,282,400
|
C
|
|
2008
|
|
 |
|
* C indicates Complete; IP indicates In Progress; NS indicates Not Started; D indicates Delayed |
|
 |
|